How the vehicles come together.

Assembly progress, ring by ring, and the pace supported by the record.

FROM THE PHOTOGRAPHIC ARCHIVE

Black-and-white close-up of a Starship stack with people beside the vehicle.
The scale of a Starship stackArchive · 10 Aug 2021 · Starship and Super Heavy Stack · SpaceX · CC BY-NC 2.0. Resized; display crop may apply.

Section claims

Stacking pace

Compare the ledger's named section steps from day zero. A move stays a move and a note stays a note. Neither claims a stack was completed. Every mark and filled table cell opens its ledger claim.

Both charts use the same day scale. Scroll charts and tables sideways on a phone. How to read this · Build pipeline

Ships

Days since each vehicle's first named section claim. Circle: move. Square: stack. Triangle: note. Solid ink: confirmed. Open orange: unconfirmed. ? beside a vehicle: unconfirmed baseline. Separate marks on the same day are offset vertically.

No first section claim: S45, S43, S42, S41, S40, S39, S38, S37, S36, S35, S34, S33, S31, S30, S29, S28, S25, S24.

Boosters

Boosters: days since first named section claim01020304050B24 first section: 2026-09-27 confirmedB24B24: Move A2:4 to mb1; 0 days; 2026-09-27; c-ff4fd9d58c2c; confirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB24: Move A5:4 to mb1; 5 days; 2026-10-02; c-e359a91b19a5; confirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB24: Move A6:4 to mb1; 10 days; 2026-10-07; c-97af2ce5756b; confirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB24: Move CH4-landing-tank to mb1; 10 days; 2026-10-07; c-31a3d179a70e; confirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB24: Move transfer-tube to mb1; 11 days; 2026-10-08; c-b4153be772d9; confirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB24: Move LOX-landing-tank to mb1; 17 days; 2026-10-14; c-6c55320d4099; confirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB24: Note A2:4 at mb1; 23 days; 2026-10-20; c-0eb9b4717362; unconfirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB24: Note F3:4 at mb1; 27 days; 2026-10-24; c-e12074bf2180; unconfirmed; first section 2026-09-27 c-ff4fd9d58c2c confirmedB23 first section: 2026-09-08 confirmedB23B23: Move AX:2 to mb1; 0 days; 2026-09-08; c-cf88d6f1d4ac; confirmed; first section 2026-09-08 c-cf88d6f1d4ac confirmedB23: Move F2:4 to mb1; 1 days; 2026-09-09; c-6c712e92b0ff; confirmed; first section 2026-09-08 c-cf88d6f1d4ac confirmedB23: Note F3:4 (site unstated); 13 days; 2026-09-21; c-298cd3aa0b22; confirmed; first section 2026-09-08 c-cf88d6f1d4ac confirmed
Days since each vehicle's first named section claim. Circle: move. Square: stack. Triangle: note. Solid ink: confirmed. Open orange: unconfirmed. ? beside a vehicle: unconfirmed baseline. Separate marks on the same day are offset vertically.

No first section claim: B25, B22, B21, B20, B19, B18, B16, B15, B14, B13, B12, B11, B10, B9, B7.

How to read this

Fleet scope is every catalogued ship and booster, including vehicles with no section claims. A blank says nothing about their build status.

  • Day zero is the earliest dated claim whose effect explicitly names a section of that vehicle: a slot move, stack, unstack, or note about a slot. An unstack can establish day zero but is not a stacking step.
  • A step is a move to a named destination, a stack at a site, or a note about a named section at a site. An unstated site stays unstated. Each distinct kind, section and site gets a column, using its earliest claim. Repeated mentions do not replace that claim.
  • Earliest means claim date, then seq, then claim id. Unconfirmed claims are kept and labelled. An unconfirmed first section makes elapsed times provisional too.
  • Days are whole calendar days between claim dates in UTC. Report dates stay report dates. Summary wording, profiles, whole-vehicle moves, future plans and later milestones never supply missing dates or stages.